NATIONAL STRATEGY
In 2025, Spain continued to solidify its regulatory and governance framework for marine renewable energies — including wave, tidal and other oceanenergy technologies — without issuing a dedicated new national strategy. The strategic context remained anchored in the Integrated National Energy and Climate Plan (NECP / PNIEC 2023–2030), updated and approved by Royal Decree 986/2024 in September 2024, whose provisions guided policy implementation.
On Ocean Energy, the overall policy context remains guided by the Roadmap for Offshore Wind and Marine Energies (published in 2021), which remains the primary high-level reference for the sector.
Regulatory Framework (2025)
The Royal Decree 986/2024 applies to marine energy technologies beyond offshore wind and confirms that innovative installations below 20 MW remain exempt from competitive tendering, thereby facilitating early-stage demonstration deployments. Full environmental and administrative procedures remain mandatory (Environmental Impact Assessment, concession for maritime terrestrial public domain, etc.), while detailed parameters of competitive allocation for larger projects will be further defined through subsequent Ministerial Orders.
In November 2025, the Spanish government approved Royal Decree RD 997/2025 of November 5, 2025, which approves urgent measures to strengthen the electricity system. In particular, “Article 8. Administrative authorizations for standard generation projects on R&D platforms” includes provisions to facilitate the deployment of test platforms and R&D projects in the energy sector, facilitating plug-and-play connections for technology demonstrators on R&D technology platforms in the marine environment.
Marine Spatial Planning (MSP)
Spain’s Maritime Spatial Plans (POEM) — approved in 2023 under RD 150/2023 — continued to serve as the spatial governance basis in 2025. During the year, Spain advanced the Second Cycle of MSP through multistakeholder workshops coordinated by MITECO and CENEAM, ensuring representation of marine renewable energy developers and research institutions in discussions on coexistence, environmental protection and spatial prioritization.
MARKET INCENTIVES
There are no specific market incentives for ocean energy in Spain, but for renewable energy installations in general.
Royal Decree 413/2014, of June 6th, established that the support for new renewable facilities is granted through competitive public tender processes. Through these auction processes, bidders propose the initial value for the investment that they will be willing to accept, and the MW auctioned are allocated to the most competitive offers (the lower ones).
Royal Decree 960/2020, of November 3rd, which regulates the economic regime of renewable energies for electricity production facilities and Order TED/1161/2020, of December 4th, which regulates the first auction mechanism for the granting of the economic regime of renewable energies, will allow to start the tender calendar for the next years. The above-mentioned Order TED/1161/2020 establishes a tender of 20 MW every two years focused on “Other Technologies”, where ocean energy is included.
PUBLIC FUNDING PROGRAMMES
In 2025, Spain advanced the execution of EUfunded support schemes for marine renewables under the Recovery, Transformation and Resilience Plan (PRTR):
Spain also provides access to broader national R&D funding programmes that, while not specific to ocean energy, are widely used by developers and research institutions in the sector. Instruments from CDTI—such as PID and CIEN—support industryled innovation through collaborative projects, while the State Research Agency (AEI) funds fundamental and applied research through competitive national calls. These mechanisms have been effectively leveraged to advance oceanenergy technologies in areas like materials, PTO systems, and environmental monitoring, complementing sector specific programmes and strengthening Spain’s overall innovation ecosystem for marine renewable energy.
MARINE SPATIAL PLANNING POLICY
There is no specific Marine Spatial Planning (MSP) policy.
Pre-selected areas for ocean energy development have not been defined. Site selection is carried out on a case-by-case analysis. In the Basque country, in the case of Biscay Marine Energy Platform (BIMEP), a MSP approach was used for selecting the site.
AUTHORITIES INVOLVED
The authorities involved in the consenting process are:
CONSENTING PROCESS
The total time needed to obtain approval is approximately two years but this timeframe varies between projects.
For instance, consenting of BIMEP started in July 2008 and ended in 2012 with the concession of marine-terrestrial public domain and the authorization for project execution. In contrast, the consenting of the Mutriku wave power plant took less than two years as it is located onshore and consequently was subject to the consenting process applicable for an ‘ordinary’ renewable energy plant. The reason for such time variability to obtain the final consent is attributed to whether an Environmental Impact Assessment (EIA) is required or not.
The new EIA law in Spain since 2013 aims to reduce the time scale needed for obtaining the Environmental Authorization, establishing a time period of no more than 4 months, or 6 months if there are justified reasons, thus reducing significantly the time needed for this consenting process which was about 3 to 24 months according to the previous law from 2008.
The Ministry of Industry, Tourism and Commerce, through the Energy Policy and Mines Directorate-General, is the decision-making body and it is responsible for granting the administrative authorization. However, in practice, there are more bodies involved in the process and developers need to deal with them.
ENVIRONMENTAL IMPACT ASSESSMENT
An EIA is assessed on a case-by-case basis.
According to Law 21/2013, of 9 December, all projects devoted to the production of energy on the marine environment are subject to be evaluated through a simplified environmental impact assessment process. The entity responsible for the decision on whether an EIA is required or not is the Ministry of Agriculture, Food and Environment.
There are not too many experiences related with EIA baseline and post-monitoring steps. The most interesting case can be BIMEP where an environmental monitoring plan was carried out. For example, this included monitoring activities during the installation of the electrical cables.
LEGISLATION AND REGULATION
In Spain, no dedicated consenting process exists ocean energy technologies.
The consenting process is based on three main legal instruments that are briefly outlined here.
Legislation and regulation that have been adapted to better suit ocean energy:
CONSULTATION
Consultation is usually required as part of the legal licensing process. It is usually made after the Environmental Impact Statement is delivered to the authorities for approval.
Advices are asked by the licensing authority to a number of statutory consultees namely Institute of Nature Conservation, port authorities and a number of public authorities responsible for marine resources management.
There are informal consultation activities implemented during the licensing process: usually developers prepare a number of informal public events to disseminate the project and collect the public feed-back on their activities at sea.
GUIDANCE AND ADVICE
It is clear to applicants what permits are required, in what order and what information must be supplied at what time, but no specific guideline (single document) is available for developers.
TEST CENTERS
Deployment at Bimep is already pre-consented so developers do not have to submit a full application comprising all the typical consents providing certain initial conditions are met.